My good friend, Harvey
Levine, has a fine sense of humor. The other day I had occasion to refer
to his book: Practical Project Management, Tips, Tactics, and Tools[1]
on the subject of estimating. Harvey says that he could devote a whole
chapter to the subject of estimating task duration. Further, he
emphasizes the importance of this activity by stressing that a project
schedule is the result of aggregating all the task durations and that if
these lack validity, so does the entire project schedule.
Then he turns the question
around and asks ...
How Long Does It Take to
Catch a Fish? |

Clique aqui para maiores detalhes |
"Here's a good question. How long does it
take to catch a fish? Ridiculous, you say. One can't estimate the time to
catch a fish. It could be just after you cast a line in the water. It might
be never. Or anywhere in between. As ridiculous as this sounds, that is just
the feeling that goes through our minds when we are asked to estimate the
duration for a task. Our first thought is How the h*** should I know? But we
can't get away with this. So we dig in and take a scientific stab at the
task duration.
First, we come up with a most likely estimate
of the duration. This is the time that we feel it would take about 50
percent of the times that we were to execute the task. But we're not
comfortable with a 50 percent confidence factor. So we add some time that we
feel we could support about 90 percent of the time.
Next, we think about what we will need to
start the task, including what kinds of conditions are required. If we are
concerned that we will not have everything that we need to start the task,
we add some more time to the task estimate (even though these issues do not
impact upon the actual time to execute the task itself).
Then there is the collection factor. When a
group of tasks come together, we tend to add some more safety margin, to
allow for one of the tasks to slip. Similarly, we note that there is a
tendency to lose time between tasks. I call this the 5 + 5 = 13 rule. Two
tasks, each estimated at 5 days, performed in series, will take 13 days
because we lose 3 days between the completion of the first task and the
start of the second task.
So what do we do? We compensate for all these
factors that are external to the immediate task, by adding time to the task
estimate, itself.
Finally, everyone knows that
the total duration will not be accepted. They expect to be pushed for a 20
percent reduction, so they add 25 percent to the already inflated estimate."[2]
But Harvey is not yet finished.
Estimating the task duration is only the start. What happens when it comes
to doing the task? How long does it take? On this part, Harvey has this to
say ...
The Psychology of Task
Durations
"There is a self-fulfilling prophecy
regarding performance of tasks within planned durations. A task is hardly
ever completed ahead of schedule. There are several reasons for this. We can
demonstrate these using an illustration of a task that has a 50-50 chance of
being completed in 5 days, but has been scheduled for 10 days to allow for
uncertainty, risk, emergency diversions, and so on.
First, there is Parkinson's Law. Work expands
to fill the time available for the work. Work on the task has commenced on
schedule and is essentially completed within the first 5 days. But, because
10 days have been allocated for the task, the performer spends the next 5
days fine-tuning the deliverable. This is a natural work ethic of most
people. We reach 98 percent completion on our task and, if additional time
is available, we attempt to refine it until a delivery deadline is reached.
Second, is procrastination. We are able to
start the task as scheduled. But, because there are 10 days allocated, and
we know that we need only 5 days, we wait a week to start the task. Now, of
course, the contingency has been exhausted before the task has been started,
and the potential for a schedule overrun has been increased. But, even if
there are no problems, the 5-day task has taken 10 days.
Less obvious are the subtle
motivators to avoid early completion of tasks. If we estimated 10 days and
complete the task in 5 days, we might be criticized for padding the estimate,
even though the extra 5 days was a legitimate allowance for uncertainty. Or
we might be under increased pressure to shorten duration estimates in the
future. There rarely is a reward for finishing tasks early - only demerits
for running over. So where is the motivation to do the task in 5 days?"[3]
So, Harvey offers this tip to
project managers:
"The time to complete a task
will almost always take a minimum of the allocated time, and probably more.
If pressure is to be maintained to minimize the time spent on tasks, it is
advantageous to move most contingency out of the individual tasks and allow
for contingency in other ways."[4]
Amen to that! And there is a
whole heap more good advice in this fascinating book of Harvey's practical
experience.

1. Levine, H. A.,
Practical Project Management, Tips, Tactics, and Tools, Wiley, NY, 2002
2. Ibid, Chapter 3.3, pp93-94
3. Ibid, pp97
4. Ibid.
Copyright© 2006 Max Wideman
____________________________________________________________________________
Se você também
deseja participar desta seção, envie e-mail para
artigos@tenstep.com.br
Teremos o maior prazer em publicar seu artigo.
|